Case Study 2

Image
  Place of Operation: RHIP, Salalah, Oman Date of Execution: December-2018 to April-2019 Criticality: High Background : Prior to Minimac being involved in the project, in August 2018, as a part of the pre-commissioning activity, flushing of 14 compressors and heat exchangers (ACHE, Picture 2) was performed and completed by a service provider. But soon after in the month of October, during the commissioning of the compressor, large debris deposits were found getting generated and collected in the in-line lube oil filter. The debris consisted of silica, metal shaving, and a lot of chunky particles. The commissioning activity was immediately stalled, leading to a threat to the project timeline and subsequent financial loss for the EPC company and the Operating company - PDO. Problem Statement : Large particle contamination detection in the inline filters of all heat exchangers and compressors during the commissioning stage, even though flushing was completed as a part of the pre-comm