Case study
Place: A steel plant in Rourkela with production capacity - 4.5 MTPA Date of Execution: 20th July 2019 Equipment Criticality: High Background: A Steam turbine blower was to be commissioned in a steel plant by a leading EPC company, the pipelines were erected on the site and as per the Standard Operating Procedure listed by the Steel Plant Owner Company the flushing was completed with a single auxiliary pump at 1500 LPM. However, during the trial run of the turbine, the inline lube oil filters would clog very frequently and lead to halted operations. Problem Statement: Frequent clogging of inline lube oil filters were hindering the operations and delaying the steam turbine commissioning project Underlying Issues: On inspection, a root cause analysis was done and the required rate for effective flushing was calculated as 3500 LPM. The Particle contamination level was also found to be NAS 10. Hence following things were concluded: 1. The rate at which flushing was done was ...